管道、阀门及仪表的安装文件翻译中英文对照

三. 安装前的准备工作III.
Preparation before installation
1. 组织人员的配备:
1. Arrangement of personnel organization:
装置安装必须有专业人员负责,有检修工、配管工、起重工、电焊工及辅助工参加。
The device installation should be taken charge of by the professional staff and requires the participation of the repairer,
the pipe fitter, the lifting worker, the electric welder and the auxiliary worker.
2. 组织有关人员熟悉《压力容器安全监察规程》、装置图纸等,以便于了解和掌握安装、起重、运行操作等事项。
2. Organize the persons concerned to get to know Pressure Vessels Safety Supervision Regulation, the drawings for the device,
etc, in order to learn the installation, lifting, operation and other items. 
3. 确定安装地点
3.  Confirmation of installation place
3.1安装地点应尽量接近用供汽地点,目的在于缩短输汽管路,降低管路散热损失。
3.1 The installation place should be near the place of steam consumption and supply for the purpose of reducing the steam
transmission pipe and lowering the pipeline heat loss.
3.2给水排水方便。
3.2 It should be convenient for water supply and drainage.
3.3运输道路畅通。
3.3 The transport road is smooth.
3.4装置空间布置应符合有关规定。
3.4 The arrangement of device space is in accordance with the pertinent regulations.
4. 安装位置确定后应按装置地基尺寸砌地基。
4. After the installation position is confirmed, lay the foundation according to the foundation size of the device.
5. 设备验收:
5. Equipment acceptance:
5.1复核设备完整性,并检查装置在运输中是否损坏变形等情况。
5.1 Check the completeness of the equipment and inspect whether the device is damaged or deformed during the transportation.
5.2装置大件在卸车时应注意,不可损坏装置的各个部分。
5.2 Pay more attention to the big device when unloading the vehicle and never damage any part of the device.
四. 装置本体的安装
Installation of the device body
  装置本体吊于基础上,找正就位,应考虑装置间的膨胀连接。
The device body is hoisted above the foundation and put in place. It is also required to consider the expansion connection
between devices.
五. 管道、阀门及仪表的安装
Installation of pipeline, gate an instrument
1. 管道、阀门、仪表应安装平整、正确,电动泵应固定在适当位置,并接通电源进行试运转,不可有振动、噪声及反转等现象。
1. The installation of the pipeline, gate and instrument should be proper and even. The electric pump should be fixed in
place and powered on for trial run and cause no vibration, noise and inversion.
2. 安全阀应在装置进行水压实验后安装,并应安装排气管。
2. The safety valve should be installed after the water pressure test for the device is finished and the exhaust pipe is also
required to be installed.

华译网上海翻译公司曾经翻译过大量有关管道、阀门及仪表的安装资料文件,Beijing Chinese Subtitling Translation Service Agency has translated many technical documents about Installation of pipeline, gate an instrument.
3. 排污管应接到固定的管排处,防止排污时管道移位及发生水击等事故。
3. The drainage pipe should be connected to the fixed pipe drainage place to avoid the pipeline displacement and the water
hammer when draining the sewage.
4. 装压力表时应使刻度盘端正,并应在2.35Mpa压力刻度处标示红线。
4. The installation of the pressure gauge should ensure the dial upright and indicate the red line at the pressure scale of
2.35Mpa.
六. 总体水压试验
General hydraulic pressure test
装置的承压系统及其附属装置组装完毕后,应按JB1612锅炉水压试验技术条件进行水压试验,安全阀应在水压试验合格后安装。
After the pressurized system of the device and its auxiliary device are assembled, it is required to conduct the hydraulic
pressure test in terms of the technical condition of JB1612 boiler hydraulic pressure test; the safety valve can be installed after the hydraulic pressure test is qualified.
1. 水压试验前应做好下列准备工作
1. Do the following preparations before the hydraulic pressure test
1.1进行承压部分的内部清理和表面检查。
1.1 Clean the internal pressurized parts and inspect their surfaces. 
1.2检查管子有无堵塞。
1.2 Check whether the pipe is blocked.
1.3装妥校验合格的压力表(不应少于2只)量程为试验压力的1.5~3倍。
1.3 The range of the qualified installed pressure gauge (at least two gauges) is 1.5~3 times of its test pressure.
1.4装妥排水管道,打开放气阀,压死安全阀座。
1.4 Install the water drainage pipeline, open the exhaust valve and press down the safety valve seat.
2. 水压试验应符合下列要求
2. The hydraulic pressure test should conform to the following requirements:
2.1水压试验应在环境温度高于5℃时进行,否则应采取防冻措施。
2.1 The hydraulic pressure test should be done when the ambient environment is higher than 5℃. Otherwise, it is required to
adopt anti-freezing measures.
2.2系统充满水后,金属表面如有结露,应予消除。初步检查无漏水,然后缓慢升压,当升至2.35Mpa时,应进行一次检查,必要时可拧紧人孔
、手孔和法兰等螺栓。
2.2 After the system is filled with water, if the metallic surface has condensation, remove it in time. No water leakage is
found in the preliminary inspection; boost the pressure slowly. When the pressure reaches to 2.35Mpa, inspect it again and screw down the manhole, hand hole and flange bolts if necessary.
2.3试验压力:
2.3 Test pressure:
蒸汽聚集器水压试验压力Ps =3.3MPa
The pressure for the hydraulic pressure test of steam accumulator Ps =3.3MPa
其余各个设备单体水压试验压力Ps = 1.5P=1.5×2.5=3.75Mpa 。
For the hydraulic pressure test of the other single equipment, Ps = 1.5P=1.5×2.5=3.75Mpa.
装置水冷系统的试验压力Ps =3.3MPa 。
The test pressure of the device water cooling system Ps =3.3MPa.

上一页   下一页
翻译语种 更多>>
英语翻译 德语翻译 法语翻译
俄语翻译 日语翻译 韩语翻译
西班牙语 葡萄牙语 荷兰语翻译
乌克兰语 意大利语 波兰语翻译
丹麦语翻译 希腊语翻译 泰语翻译
瑞典语翻译 越南语翻译 阿拉伯语
专业范围 更多>>
· 安全环保 · 能源电力 · 银行保险
· 法律翻译 · 天文地理 · 钢铁冶金
· 航空航天 · 道路桥梁 · 地质采矿
· 建筑工程 · 金融财会 · 经济管理
· 交通运输 · 仪器仪表 · 医疗器械
· 医药卫生 · 石油化工 · 机械电子
译者 更多>>
· 法语机电专业翻译 张先生
· 法语财经专业译者--王先生
· 法语金融保险专业译者 --...
· 法语翻译石油化工专业译者 ...
· 德语电子专业翻译 黄女士
· 德语法律专业翻译 李先生
· 德语医药翻译 赵女士
· 法语机电专业翻译 张先生
· 法语财经专业译者--王先生
· 德语财经金融保险专业译者 ...
· 德语石油化工专业译者 --...
· 法语金融保险专业译者 --...
· 法语翻译石油化工专业译者 ...
业绩 更多>>
· 德语翻译项目部分成功案例介绍
· 法语翻译项目部分成功案例介绍
· 葡萄牙语翻译项目案例介绍
· 意大利语翻译部分项目列表
· 西班牙语翻译部分项目介绍
· 俄语翻译部分项目介绍
· 日语翻译部分项目
· 小语种部分翻译项目介绍
上海漕溪北路38号20G 电话:021-31200158 shkehu@263.net,QQ:390645976
北京海淀区太阳园4号楼1507室 电话:010-82115891 82115892 bjhyw@263.net QQ:800022641
太原市万柏林区迎泽西大街奥林匹克花园7D202 电话:15034183909 Email:tykehu@163.com
京ICP备05038718号-15